Marella development, ENNISCRONE, Co SLIGO

Client: ERNST & YOUNG

Project Background:

Establish the cost of completing and fitting out 23nr houses at the above address to a 4 star Board Failte standard and associated site works. Drainage works surveyed and report established.

BHL Role:

  • Produce a cost report on the cost to finish 23nr houses and establish cost to rectify the drainage works for the houses and the associated Hotel
  • Nominated contractor’s to Ernst and Young for remedial works

Completion:

  • April 2009